County GovernmentThursday, November 19
Missoula County accepts a data center study and starts work toward permanent rules
The Good Day Missoula team
Missoula County is moving toward permanent data center rules. Commissioners unanimously accepted a study last Thursday that looked at 13 categories of impacts, from noise and water to wildlife and climate change.
Missoula County commissioners unanimously accepted the data center study
Missoula County commissioners vote, Nov. 12
3–0
Accept the data center impacts study and approve its recommendations
Yes 3
- Strohmaier
- Slotnick
- Vero
Source: Montana Free Press
View as table
| Member | Seat | Vote |
|---|---|---|
| Dave Strohmaier | Yes | |
| Josh Slotnick | Yes | |
| Juanita Vero | Yes |
County planner Patrick Swart said even smaller data centers can have impacts, and the average modern one needs about 40 megawatts of electricity.
40 megawattsaverage power demand of a modern data center
That's equivalent to the power demand of all the homes in Missoula, Swart said.
Source: Montana Free Press
The vote lets staff start on permanent rules, but it could be another year before they're in place. County staff suggested waiting until after the Legislative session, because Montana's "Right to Compute Act" could override local zoning.
“To give folks some level of comfort, there will be no gap.”
- Moratorium: started in July; extension called the likelier case
- Power costs: advocates want data centers, not ratepayers, to pay
- County intends a role in Public Service Commission rate setting
Sources: Montana Free Press, Montana State News Network